问题描述
升级双节点MetroCluster 期间、切换失败。
clusterA::> metrocluster node show
DR Configuration DR
Group Cluster Node State Mirroring Mode
----- ------- ------------------ -------------- --------- --------------------
1 clusterA
nodeA-1 configured enabled negotiated switchover incomplete
clusterB
nodeB-1 configured enabled negotiated switchover pre-commit completed